Bproc - How to configure Due Date for User Task?

Hi,

How to set Due Date for user task in Bproc? I want to set the due date like 2 days / 3 days from the initiation date.

Thanks,
Hari

Hi,
all possible ways to define a task due date is described in Flowable documentation. If you want to set a period you can use the ISO8601 time-duration format (for example, P2D means 2 days)

If i ever withdraw this post would have been by mistake, please don’t delete it.